Passenger trains between Budapest and Belgrade delayed beyond December

UrbanismNovember 14, 20262-minute read
Passenger trains between Budapest and Belgrade will not resume service in December either
Passengers have been waiting for months for services to begin on the railway running south from Budapest, but the line will remain closed to passenger trains during the next timetable period. Services between Budapest and Belgrade have been left out of the new timetable taking effect on 13 December, Világgazdaság reported.

No new launch date has been announced.

Software problems found during testing

Dávid Vitézy, Hungary’s transport and investment minister, said on Friday night that the line had undergone particularly extensive testing in recent weeks. He said the close scrutiny was needed because this was the first railway in Hungary where a Chinese manufacturer had installed a safety system designed to meet European standards.

The tests identified several smaller problems, mainly affecting software, in the train-control system installed by the Chinese contractor. The faults must be repaired before the testing process can begin again. Vitézy said passenger services would be allowed to start only after the relevant authority, quality-assurance body and certification organisation were all satisfied that the system worked properly.

Alongside MÁV, Hungary’s state railway company, and the Hungarian authorities, the independent quality-assurance organisation TÜV is also involved in the tests. Vitézy said the decision to bring in TÜV had been made earlier by János Lázár and that he had kept the arrangement in place after assuming ministerial responsibility for the project.

The Austrian and Serbian railways had previously announced plans for a December launch. According to Vitézy, those announcements were based on information provided by MÁV after earlier tests had been completed successfully. The more recent faults mean that passenger services have not been included in the timetable starting on 13 December.

The launch date has shifted several times

In early October, domestic passenger services still appeared to be close. Vitézy said at the time that load testing and checks of the ETCS train-control system had been completed successfully on the Hungarian section. The final documentation was expected by mid-October, with domestic passenger trains potentially starting in the second half of the month.

By early November, the minister told RTL Híradó that he had been optimistic at the time. He added that he had not heard of any concern that would prevent services from beginning within the foreseeable future.

Freight traffic began in February rather than last November as originally planned. Before passenger services can start, the contractor must also complete a final track realignment under the warranty. Vitézy described this as a job lasting almost two months, covering station tracks, points and the open line to prepare the railway for long-term operation at 160 kilometres per hour.

Vitézy also said he had previously criticised the route, cost and business model of the project. According to figures published by Világgazdaság, the Hungarian section cost HUF 800 billion, with 85 per cent financed through a Chinese loan.

Source: Világgazdaság